# Tin Can Production Line Installation and Commissioning: Complete Guide from Delivery to Full Production
## Key Takeaways
– A complete tin can production line project — from contract signing to full rated output — typically requires **4 to 8 months**, depending on line complexity, destination country, and site readiness.
– The single largest cause of installation delays is **unfinished site preparation**: utilities (power, compressed air, cooling water), foundation, and factory clearances are rarely ready when equipment arrives.
– **Factory Acceptance Testing (FAT)** at the supplier’s plant eliminates the majority of mechanical and control issues before shipment; skipping FAT significantly increases on-site commissioning time and cost.
– **Site Acceptance Testing (SAT)** should include quantified metrics written into the contract: rated CPM, yield threshold, continuous run duration, and dimensional tolerance — not vague “satisfactory performance” language.
– A structured **ramp-up period of 2 to 6 weeks** is normal; attempting to reach rated speed on day one leads to excessive scrap, tooling damage, and operator frustration.
– Training should be layered by role — operators, setup technicians, maintenance staff, team leaders — with both classroom and hands-on components; plan for a minimum of 10 to 15 working days of on-site training.
—
## Introduction
Signing the contract is a milestone, but it is not the finish line. For buyers investing in a tin can production line — whether a single 30 CPM square can line or a multi-line plant expansion — the real challenge begins after the purchase order is confirmed. Equipment must be manufactured, tested, shipped across borders, installed, commissioned, accepted, and gradually ramped to full production.
According to **SMMEc (2024 Global Manufacturing Report)**, capital equipment projects in the light manufacturing sector experience an average schedule overrun of 18–25%, with site readiness cited as the primary root cause. In the metal packaging industry, where line speeds exceed 60 cans per minute and sealing tolerances are measured in tenths of a millimeter, installation quality directly determines whether the line produces saleable cans or endless scrap.
This guide covers every stage of the installation and commissioning process, drawing on **Jiujiang Yongxin Can Equipment Co., Ltd.**’s experience delivering production lines to domestic and international customers since 2005. Whether you are a first-time buyer setting up a greenfield factory or an established manufacturer adding capacity, this article provides the framework, timelines, checklists, and contract considerations you need to move from delivery day to full production with confidence.
The metal packaging industry demands precision. A double seam that is 0.1 mm off-spec can leak; a welding electrode dressed 0.5 mm too aggressive can cause burn-through; a servo position drifting by 0.3 mm can produce out-of-tolerance can heights at 60 CPM. These are not theoretical concerns — they are daily realities on the production floor. The installation and commissioning process is where these tolerances are established, verified, and handed over to the production team. Getting this phase right determines the line’s performance for years to come.
For context on earlier buying stages, see [How to Choose a Tin Can Making Machine Manufacturer](https://canmachine.org/how-to-choose-tin-can-making-machine-manufacturer-china-2026/) and [Tin Can Making Machine Price Guide](https://canmachine.org/tin-can-making-machine-price-guide-china-2026/).
—
## 1. Project Timeline Overview: From Contract to Full Production
A tin can production line project follows a defined sequence. Total duration varies by line type, customization level, shipping distance, and site readiness.
### Table 1: Complete Project Timeline — Typical Durations and Deliverables
| Phase | Typical Duration | Responsible Party | Key Deliverable | Payment Milestone |
|——-|—————–|——————-|—————–|——————-|
| Contract & technical agreement | 1–2 weeks | Buyer + Supplier | Signed contract, technical appendix | Deposit (typically 30%) |
| Pre-payment & production scheduling | 1 week | Supplier | Production order released | Pre-payment received |
| Manufacturing & in-process QC | 6–12 weeks | Supplier | Weekly progress reports | — |
| Factory Acceptance Test (FAT) | 2–5 days | Supplier + Buyer witness | FAT report, punch list | Pre-shipment payment (typically 60%) |
| Packaging & dispatch | 3–7 days | Supplier | Packing list, loading photos | — |
| Ocean freight / land transport | 2–6 weeks | Logistics / Buyer | Bill of Lading | — |
| Import customs clearance | 3–10 days | Buyer / customs broker | Customs release | — |
| Delivery to site & unpacking | 1–3 days | Buyer + carrier | Unpacking inspection report | — |
| Installation | 1–4 weeks | Supplier engineers + Buyer crew | Installation completion report | — |
| Commissioning & trial run | 2–3 weeks | Supplier engineers + Buyer operators | Parameter sheet, line balance report | — |
| Site Acceptance Test (SAT) | 2–5 days | Supplier + Buyer joint | SAT certificate | Final payment (typically 10%) |
| Ramp-up production | 2–6 weeks | Buyer (Supplier support as needed) | Ramp-up curve, yield report | Warranty begins |
> **Note**: Total elapsed time is typically **4–8 months**. For starting a can manufacturing operation from scratch, see [How to Start a Tin Can Manufacturing Business](https://canmachine.org/how-to-start-tin-can-manufacturing-business-china-2026/).
—
## 2. Pre-Installation Preparation: The Most Delay-Prone Phase
The period between contract signing and equipment arrival is an active preparation window. The most common reason schedules slip is not equipment delay — it is the buyer’s facility not being ready.
### 2.1 Technical Agreement Refinement
Before production begins, the technical agreement must specify:
– **Can specifications**: dimensions, material type (tinplate, TFS, aluminum), thickness range (e.g., 0.16–0.4 mm per Yongxin’s range), end type.
– **Line speed (CPM)**: rated speed and tolerance. Yongxin’s 1–5L small square can fast line: 45–60 CPM; standard line: 30–35 CPM.
– **Electrical specs**: voltage (380V standard), frequency (50/60 Hz), phase, control voltage.
– **Compressed air**: pressure (0.6–0.8 MPa), flow rate, air quality class.
– **PLC/HMI language** and optional equipment (auto lid feeding, conveyors, palletizers).
### 2.2 Layout Drawing & Utilities
The supplier provides a GA drawing showing machine footprints, maintenance clearances, and material flow. The buyer must approve this against their actual factory space. Yongxin’s 10–20L large square can line, for example, measures 15,000 × 1,600 × 2,700 mm and weighs 17,750 kg — the factory must also accommodate conveyors, raw material staging, and accumulation tables.
### Table 2: Utility Requirements by Line Type
| Utility | Small Square Line (30–35 CPM) | Fast Line (45–60 CPM) | Large Square Line (25–32 CPM) | Small Round Line (30–40 CPM) | High-Speed Round (60–80 CPM) |
|———|——————————-|———————-|——————————-|——————————|——————————|
| Total installed power | 18 kW | 45 kW | 55 kW | 8 kW | 12 kW |
| Supply voltage | 380V / 3-phase | 380V / 3-phase | 380V / 3-phase | 380V / 3-phase | 380V / 3-phase |
| Compressed air | 0.6–0.8 MPa | 0.6–0.8 MPa | 0.6–0.8 MPa | 0.6–0.8 MPa | 0.6–0.8 MPa |
| Air flow | ~0.3 m³/min | ~0.5 m³/min | ~0.6 m³/min | ~0.2 m³/min | ~0.4 m³/min |
| Floor loading | ≥500 kg/m² | ≥800 kg/m² | ≥1,000 kg/m² | ≥400 kg/m² | ≥600 kg/m² |
> **Important**: The large square can line (55 kW, 17,750 kg) requires significant electrical infrastructure. Confirm transformer capacity with your utility provider. For unstable grids, a dedicated voltage stabilizer for the PLC system is recommended.
### 2.3 Foundation, Floor & Building Requirements
– **Floor flatness**: ±2 mm/m for main sections; tighter for high-speed lines (45+ CPM).
– **Foundation**: Standard industrial slabs (≥200 mm reinforced concrete) typically suffice; heavy stamping operations may need isolated foundations.
– **Anchor bolts**: Install sleeves or chemical anchor inserts per supplier drawings before machine positioning.
– **Ceiling height**: Minimum 4 m; 5+ m for overhead conveyors or crane access.
– **Crane/hoist**: Lines over 5,000 kg (e.g., 10,000 kg fast line, 17,750 kg large line) require adequate lifting capacity.
– **Door dimensions**: The fast line’s main frame (12,000 × 2,000 × 2,400 mm) may need sub-assembly for entry through standard doors.
### Table 3: Customer Preparation Checklist — Items That Directly Impact Schedule
| Item | Consequence of Delay | Lead Time |
|——|———————|———–|
| Power supply connection | Cannot power up for commissioning | 4–8 weeks before arrival |
| Compressed air system | Pneumatic actuators cannot function | 3–6 weeks |
| Floor preparation & curing | Machines cannot be leveled or secured | 2–4 weeks |
| Cooling water piping | Overheating during extended runs | 2–4 weeks |
| Crane / forklift booking | Unloading delayed, demurrage charges | Confirm at booking |
| Factory clearing & cleaning | Safety hazards, installation obstacles | 1 week |
| Temporary storage area | Equipment exposed to weather | Before arrival |
| Local labor arrangement | Installation pace slows | 2 weeks |
| PLC/HMI language confirmation | Operator training delayed | At contract stage |
| Drainage | Water accumulation, slip hazard | 3–4 weeks |
—
## 3. Manufacturing Period and Factory Acceptance Testing (FAT)
### 3.1 In-Process Tracking
During the 6–12 week manufacturing period, maintain visibility:
– **Weekly progress reports** with photos showing welding, machining, assembly stages.
– **Mid-production inspection** (recommended for complex lines): verify material quality and workmanship at ~50% completion.
– **Key milestone witness points**: frame machining, main drive assembly, PLC panel wiring, pre-FAT dry run.
### 3.2 FAT Scope
FAT is the last opportunity to resolve issues before shipping. A proper FAT includes:
### Table 4: Typical FAT Test Items
| Test Category | Test Item | Acceptance Criteria |
|—————|———–|———————|
| Visual / mechanical | Workmanship, weld quality, surface treatment | No visible defects or loose fasteners |
| Electrical | Wiring, insulation resistance, grounding | Compliant with **IEC 60204-1:2016** |
| Safety function | E-stops, guard interlocks, light curtains | Per **ISO 12100:2010** and **IEC 60204-1** |
| No-load run | All stations cycle without material | Smooth operation, no abnormal noise |
| Loaded run | Material through all stations | Proper forming, flanging, seaming |
| Speed test | CPM over 10-min run | Within ±5% of rated CPM |
| Dimensional check | Sample cans measured | Within contract tolerance |
| Seam quality | Cross-section analysis | Specified overlap, tightness, body hook |
| PLC / HMI | Recipes, alarms, counting | Functions match specification |
| Safety marking | CE marking, warning labels | Per **Machinery Directive 2006/42/EC** (EU destinations) |
### 3.3 FAT Witnessing & Reporting
– **On-site witness** (preferred for complex lines): direct inspection and immediate discussion.
– **Video witness** (acceptable for single machines or repeat orders): live stream with real-time data sharing.
– **Third-party inspection** (SGS, Bureau Veritas, TUV): independent verification.
The FAT report documents date, attendees, machine ID, pass/fail per item, photographs, and a punch list. Significant non-conformities must be corrected before shipment; minor items may be rectified on-site.
> A successful FAT does not guarantee trouble-free site installation — but it eliminates the majority of mechanical, electrical, and control issues.
—
## 4. Packaging, Shipping, and Customs Clearance
### 4.1 Packaging
– **Steel-reinforced wooden crates** (ISPM 15 fumigated) for main frames
– **Pallets** for conveyors and control panels
– **Anti-rust treatment**: VCI paper or grease on machined surfaces
– **Individual wrapping** for precision components (sealing rollers, servo motors)
– **Spare parts kit** with detailed inventory list
### Table 5: Typical Shipping Configuration
| Item | Packaging | Approximate Dimensions |
|——|———–|————————|
| Main frame | Steel-reinforced wood crate | 12–15 m × 2–2.5 m × 2.5–3.3 m |
| Seaming machine | Wood crate | 1.5–3 m × 1–2 m × 1.5–2 m |
| Control panel | Plywood box on pallet | 0.8–1.5 m × 0.6–1 m × 1.5–2 m |
| Conveyors | Palletized + stretch wrap | Varies |
| Spare parts & tools | Wooden box | 0.6–1 m × 0.5–0.8 m × 0.5–0.8 m |
### 4.2 Transport & Customs
### Table 6: Transport Mode Comparison
| Factor | FCL | LCL | Break Bulk |
|——–|—–|—–|————|
| Suitable for | Complete lines in 1–3 × 40ft | Single machines | Oversized lines |
| Cost | Moderate, predictable | Higher per CBM | Highest |
| Damage risk | Low (sealed) | Moderate | Higher |
### Table 7: Required Import Documentation
| Document | Purpose | Issued By |
|———-|———|———–|
| Commercial Invoice | Customs valuation | Supplier |
| Packing List | Contents, weights, dimensions | Supplier |
| Bill of Lading | Title document | Shipping line |
| Certificate of Origin | Preferential tariff (if FTA applies) | Chamber of Commerce |
| CE Declaration of Conformity | EU import requirement (Machinery Directive 2006/42/EC) | Supplier |
| Insurance Certificate | Cargo coverage | Insurance company |
| Import License / Permit | Country-specific | Buyer’s local authority |
> **Tip**: Customs delays are frequently caused by documentation discrepancies. Review draft documents before departure and confirm HS codes with your broker.
### 4.3 Unpacking at Site
1. Photograph all crates before opening.
2. Verify crate count against B/L and packing list.
3. Open systematically, checking every item including spare parts.
4. Report discrepancies to supplier and insurer within 24–48 hours.
—
## 5. Installation Phase
### 5.1 Installation Team
### Table 8: Installation Team Composition
| Role | Qty (typical) | Responsibility |
|——|————–|—————|
| Lead installation engineer | 1 | Coordination, technical decisions |
| Mechanical technician | 1–2 | Positioning, leveling, assembly |
| Electrical / PLC engineer | 1 | Power, I/O check, PLC verification |
| Buyer coordinator | 1 | Local labor, crane scheduling, translation |
| Buyer helpers / electricians | 2–4 | Material handling, cable pulling |
### 5.2 Installation Sequence
1. Floor marking: centerlines, anchor bolt positions per approved layout.
2. Leveling pad placement or grout bed preparation.
3. Main frame positioning (the 17,750 kg large line requires 20-ton forklift or overhead crane).
4. Precision leveling (0.02 mm/m accuracy); verify inter-station heights.
5. Anchor bolting and grouting (24–48 hrs epoxy, 3–7 days cementitious).
6. Sub-assembly installation: flanging, seaming, welding stations.
7. Conveyor installation and height alignment.
8. Electrical connection: power, inter-machine cables, grounding.
9. Pneumatic connection: air supply, FRL units.
10. Safety device installation: E-stops, interlocks, light curtains.
### Table 9: Installation Duration by Line Type
| Line Type | Duration | Crew | Key Constraint |
|———–|———-|——|—————-|
| Single machine | 1–3 days | 1 tech | Leveling, power |
| Semi-auto line (2–3 machines) | 3–7 days | 1–2 techs | Alignment, sync |
| Auto 1–5L line (30–35 CPM, 2,700 kg) | 5–10 days | 2 techs | Multi-station, PLC |
| Auto fast line (45–60 CPM, 10,000 kg) | 7–14 days | 2–3 techs | Heavy lift, precision |
| Auto 10–20L line (25–32 CPM, 17,750 kg) | 10–20 days | 2–3 techs | 15 m length, complex |
### 5.3 Common Delay Causes & Prevention
| Delay Cause | Prevention |
|————-|————|
| Power not connected | Confirm contractor schedule 4 weeks prior |
| Floor not cured | Pour at least 28 days before installation |
| Crane unavailable | Book in advance; confirm capacity |
| Layout changes mid-install | Freeze after GA approval |
| Missing parts | Complete unpacking inspection first |
—
## 6. Single-Machine Commissioning and Integrated Line Trial
### 6.1 Single-Machine Commissioning
**No-load**: Verify rotation direction, lubrication, limit switches, E-stops (Category 0/1 per **IEC 60204-1:2016**), and servo tuning (e.g., Delta servo drives on Yongxin lines).
**Loaded**: Feed actual material (tinplate blanks, pre-formed bodies, or lids) through each station. Adjust station parameters: flanging depth, seaming roller pressures, welding current and speed, timing relationships. Produce sample cans, measure critical dimensions, and optimize individual station speed to approach the rated CPM. For the 1–5L small round can high-speed line (60–80 CPM), loaded commissioning is particularly important because high-speed operation amplifies any misalignment or timing error that may not be visible at lower speeds.
### 6.2 Integrated Line Trial
Link all machines: adjust buffers and synchronization, test jam detection and blockage handling, verify recipe changeover via HMI, fine-tune PLC timing and alarm thresholds.
> **Image reference**: [Production line overview — page12_1672x1394_IM267.jpg](page12_1672x1394_IM267.jpg) — Small round can production line, illustrating compact footprint and integrated station layout.
### Table 10: Commissioning Parameter Checklist
| Parameter | Method | Typical Tolerance |
|———–|——–|——————-|
| CPM | Count over 10 min | ±5% of rated |
| Can height | Caliper, 20 cans | ±0.5 mm |
| Flange width | Caliper / optical | ±0.3 mm |
| Seam quality | Cross-section microscope | Per spec |
| Weld overlap | Caliper | 0.8–1.2 mm |
| Scrap rate | Defect count / 30 min output | <3% target |
---
## 7. Site Acceptance Testing (SAT) and Acceptance Criteria
### 7.1 FAT vs. SAT
| Aspect | FAT | SAT |
|--------|-----|-----|
| Location | Supplier's factory | Buyer's facility |
| Timing | Before shipment | After installation |
| Conditions | Controlled | Actual production environment |
| Material | Supplier's test material | Buyer's production material |
| Focus | Function, safety, basic performance | Sustained output, product quality |
| Significance | Gate for shipment | Gate for final payment & warranty |
### 7.2 SAT Test Protocol
### Table 11: SAT Test Items and Acceptance Criteria
| Test Item | Description | Criteria (example) |
|-----------|-------------|-------------------|
| Rated CPM | Sustained run at rated speed | ±5%, 60 min minimum |
| Continuous run stability | Extended run, track unplanned stops | ≥4 hrs, <3 stops |
| Product quality | Dimensional + visual inspection | ≥97% within spec |
| Scrap rate | Rejected cans during sustained run | ≤3% |
| Seam quality | Cross-section examination | Per specified parameters |
| Safety re-test | All E-stops, interlocks | Function correctly in site conditions |
| Training completion | Operators run line independently | ≥2 shifts with acceptable output |
| Documentation | Manuals, diagrams, spare parts list | Complete, agreed language |
### 7.3 Writing Acceptance Criteria Into the Contract
Quantify everything:
- **CPM**: "Sustain [X] cans/min for [Y] minutes during SAT."
- **Yield**: "First-pass yield ≥ [Z]% during SAT run."
- **Continuous run**: "[N] hours without unplanned stoppage > [M] minutes.”
– **Accuracy**: “Meet tolerances in Technical Agreement Appendix [A].”
### 7.4 Handling SAT Failures
1. Identify root cause (equipment, material, or site condition).
2. Allow rectification period (typically 1–2 weeks).
3. Re-test after corrections.
4. If still failing: contractual remedies — penalty deductions, extended support, or equipment return.
> **Disclaimer**: These descriptions are general guidance and do not constitute legal advice. Consult qualified legal counsel for jurisdiction-specific contract drafting.
Upon successful SAT, sign the Acceptance Certificate and hand over: operation manual, wiring diagrams, PLC backup, assembly drawings, spare parts catalog, maintenance schedule, calibration certificates, FAT report, SAT report, and warranty certificate.
—
## 8. Ramp-Up Production: From First Cans to Full Output
### 8.1 Why Ramp-Up Matters
Reaching rated CPM on day one is unrealistic. According to **ISM (Institute for Supply Management)** guidelines, new lines typically achieve 60–70% of rated output in Week 1, 75–85% by Week 3, and full capacity by Week 4–6.
### Table 12: Suggested Weekly Ramp-Up Targets
| Week | CPM (% of rated) | Yield | Focus |
|——|——————-|——-|——-|
| 1 | 50–60% | 90–93% | Familiarization, baselining |
| 2 | 65–75% | 93–95% | Speed increase, seam optimization |
| 3 | 75–85% | 95–97% | Sustained runs, scrap reduction |
| 4 | 85–95% | 97–98% | Full-speed demo, shift handover |
| 5–6 | 95–100% | ≥98% | Full production, Cpk study |
### 8.2 Management Practices
– **Daily stand-up**: 15-minute review at the start of each shift — output, scrap rate, issues, priorities.
– **Parameter log**: Record all changes (seaming roller pressure, welding current, servo positions) along with resulting quality impact. This builds institutional knowledge for future changeovers and new operator training.
– **Scrap classification**: Categorize rejected cans by defect type (bad seam, wrong dimension, surface defect, weld failure) to identify and attack the dominant loss mechanism.
– **Gradual speed increase**: Increase CPM by 5–10% increments, holding at each level until quality is stable. Resist the temptation to jump to full speed.
– **Shift overlap**: During ramp-up, schedule at least 1–2 hours of overlap between shifts so the outgoing team can brief the incoming team on current parameters, recurring issues, and any parameter changes made during the shift.
### Table 13: Common Ramp-Up Issues
| Problem | Cause | Countermeasure |
|———|——-|—————-|
| Poor seam quality | Roll wear, wrong pressure, material variation | Cross-section analysis; adjust pressures; verify incoming material spec |
| Welding instability | Wire feed inconsistency, strip edge quality, electrode wear | Check wire tension; verify strip edge; dress electrodes on schedule |
| Frequent jams | Misaligned guides, timing errors between stations | Re-check alignment; adjust PLC timing; verify transfer clearances |
| Dimensional drift | Thermal expansion, mechanical wear, loose fixtures | Mid-shift dimensional checks; verify fixture tightness daily |
| HMI alarm confusion | Operators unfamiliar with alarm codes | Post alarm reference card at HMI; include alarm response in training |
Full production is achieved when the line consistently meets rated CPM, yield threshold, and stoppage targets for one full production week. At that point, transition from daily ramp-up meetings to routine production management.
—
## 9. Personnel Training and Team Development
Training is frequently cut when schedules compress — a false economy. According to **OSHA manufacturing guidelines**, inadequate training contributes to ~30% of equipment-related incidents.
### Table 14: Training Matrix by Role
| Module | Operators | Setup Techs | Maintenance | Supervisors | QC Inspectors |
|——–|———–|————-|————-|————-|—————|
| Machine overview & safety | 8 hrs | 8 hrs | 8 hrs | 4 hrs | 4 hrs |
| Normal operation | 16 hrs | 8 hrs | — | 4 hrs | — |
| Can size changeover | — | 16 hrs | 8 hrs | 4 hrs | — |
| Daily maintenance | 8 hrs | 8 hrs | 16 hrs | 4 hrs | — |
| Preventive maintenance | — | 8 hrs | 24 hrs | 8 hrs | — |
| Fault diagnosis | 4 hrs | 16 hrs | 24 hrs | 8 hrs | — |
| Quality inspection | 4 hrs | 8 hrs | — | 4 hrs | 16 hrs |
| Safety (LOTO, E-stop) | 8 hrs | 8 hrs | 8 hrs | 8 hrs | 4 hrs |
| **Total** | **48 hrs** | **80 hrs** | **88 hrs** | **48 hrs** | **28 hrs** |
Training combines classroom sessions (theory, safety, quality standards) and hands-on machine practice. The most effective training occurs during commissioning, when buyer’s technicians work alongside supplier engineers and see the machine’s internals — this is a once-in-a-lifetime opportunity to understand how adjustments affect can quality.
Training delivery should include:
– **Theory sessions**: machine operating principles, safety regulations, quality requirements, maintenance concepts.
– **Hands-on practice**: operating the HMI, running changeovers, responding to alarms, performing daily maintenance tasks.
– **Assessment**: written or practical test at the end of each module; operators must demonstrate independent operation before unsupervised shifts.
Deliverables: operation manual (in agreed language), maintenance manual with illustrated spare parts list, quick-reference cards posted at each station, and training certificates for each participant. For long-term maintenance planning beyond the training period, see [Tin Can Making Machine Maintenance: A Preventive Approach](https://canmachine.org/tin-can-making-machine-maintenance-china-2026/).
—
## 10. Risk Control and Key Contract Clauses
### Table 15: Contract Key Terms Checklist
| Area | Key Question | Recommended Practice |
|——|————-|———————-|
| Delivery | When must equipment be ready for FAT? | Specify date; liquidated damages (e.g., 0.5%/week, capped 5%) |
| Site prep | Who prepares foundation, utilities, labor? | “Buyer’s Scope” appendix with layout drawing |
| Installation cost | Is on-site installation included? | Specify crew size and duration |
| Travel expenses | Who pays engineers’ travel, visa, hotel? | Buyer covers local; airfare varies by contract |
| Spare parts | What is included? | Start-up spare parts list as appendix (6–12 months) |
| Warranty | When does it start and how long? | 12 months from SAT or 18 months from delivery |
| Acceptance | How is performance defined? | Quantified CPM, yield, run duration, accuracy |
| Acceptance deadline | What if SAT is delayed by buyer? | Max waiting period (e.g., 30 days post-installation) |
| Force majeure | What events excuse delays? | Standard list; clarify customs/shipping disruptions |
| Training | How many days and trainees? | Specify minimum; additional days at agreed rate |
| Disputes | How are disagreements resolved? | Governing law, arbitration (CIETAC, ICC, SIAC) |
### 10.1 Key Risk Scenarios
| Risk | Mitigation |
|——|————|
| Transit damage | Full-value insurance; photograph before unloading; report within 24 hrs |
| Site utilities not ready | Start preparation immediately after contract; track with countdown checklist (Table 3) |
| Customs delays | Experienced broker; pre-clear documents; confirm HS code in advance |
| Operator turnover during ramp-up | Train surplus personnel (plan 20% over minimum headcount); document all procedures in written SOPs and video |
| Material batch variation | Incoming inspection with defined acceptance criteria; specify material properties in technical agreement |
| Supplier engineer visa delays | Apply for business visa immediately after contract; allow 4–6 weeks for processing in some countries |
### 10.2 Company Facts
### Table 16: Company Fact Declaration — Jiujiang Yongxin Can Equipment Co., Ltd.
| Company Name | Jiujiang Yongxin Can Equipment Co., Ltd. |
| Year Established | 2005 |
| Headquarters | Jiujiang, Jiangxi Province, China |
| Patents | 86 patents (as of 2026) |
| Quality Certification | ISO 9001 (Certificate No. 107325Q1009R0S) |
| Enterprise Designation | National High-Tech Enterprise (GR202536000972, Oct 2025) |
| Provincial Recognition | Jiangxi “Specialized, Refined, Distinctive, Innovative” Enterprise |
| Product Range | Auto can lines (1–25L), single machines, food can sealers |
| Export Markets | Thailand, Vietnam, India, Saudi Arabia, expanding |
| Website | https://canmachine.org/ |
For more about Yongxin’s capabilities, visit [About Us](https://canmachine.org/about-us/). To discuss your project, reach us via [Contact](https://canmachine.org/contact-us/) or email [email protected].
—
## FAQ
### 1. How long does installation take for a 30 CPM square can production line?
For a 1–5L line at 30–35 CPM (approx. 2,700 kg, 11.75 m length), installation typically takes **5–10 working days** with 2 supplier technicians and 2–3 buyer helpers, assuming the site is fully prepared. Larger lines (e.g., 10–20L at 17,750 kg) may require 10–20 days.
### 2. What utilities do I need to prepare before the line arrives?
Minimum requirements: (1) three-phase power at specified voltage/frequency with adequate transformer capacity (8–55 kW depending on line); (2) compressed air at 0.6–0.8 MPa; (3) level, cured concrete floor with anchor provisions; (4) lighting and ventilation. See Table 2 for specifics by line type.
### 3. What is the difference between FAT and SAT?
FAT is at the supplier’s factory before shipment — verifies function and basic performance. SAT is at your facility after installation — verifies sustained production with your materials under real conditions. FAT asks “does the machine work”; SAT asks “does it produce good cans at rated speed here.”
### 4. How many engineers will come for commissioning?
Single machine: typically 1 engineer. Complete automatic line: 2–3 engineers (lead, mechanical, electrical/PLC). They remain through installation, commissioning, SAT, and initial training.
### 5. Who pays for installation, travel, and accommodation?
Common practice: if installation is included, the supplier covers salaries and usually airfare; the buyer covers local transport, hotel, meals, and visa. If quoted separately, the buyer pays the full service fee. Always clarify in the contract before signing.
### 6. What if the line doesn’t reach rated CPM during SAT?
The contract should define: (1) root cause identification, (2) rectification period (typically 1–2 weeks), (3) re-test, (4) remedies if still failing (penalty deductions, extended support, or equipment return). Quantified criteria are essential — “satisfactory performance” is not enforceable.
### 7. How long is the ramp-up period?
Typically **2 to 6 weeks**. Week 1: 50–60% speed; Week 3: 75–85%; Week 4–6: full rated capacity with stable quality. Rushing causes excess scrap and tooling damage. See Table 12 for a suggested ramp-up curve.
### 8. Do I need a special foundation?
Most lines on standard industrial slabs (≥200 mm reinforced concrete) need no separate foundation. Key requirements: ±2 mm/m flatness, anchor provisions, adequate load capacity. Heavy stamping equipment may benefit from vibration isolation. Always follow the supplier’s foundation drawing.
### 9. What spare parts come with the line?
Typically a start-up kit covering 6–12 months of wearing parts: sealing rolls, cutting blades, gaskets, O-rings, welding wire (if applicable), fuses, sensors. A detailed list with part numbers should be a contract appendix. For long-term maintenance guidance, see [Tin Can Making Machine Maintenance](https://canmachine.org/tin-can-making-machine-maintenance-china-2026/).
### 10. Can you train my operators?
Yes. On-site training is standard during commissioning — classroom (theory, safety, quality) plus hands-on (operation, changeover, troubleshooting, maintenance). Agree on a training matrix before engineers arrive. See Table 14 for a recommended structure by role.
### 11. What is the total project cost beyond the equipment price?
Budget for: shipping and insurance, import duties, local transport, crane rental, utility infrastructure, floor preparation, installation fees (if not included), engineers’ accommodation, commissioning raw materials, and labor during non-productive phases. These typically add **15–30% of equipment price** for international projects.
### 12. How do I verify double seam quality?
Through destructive cross-section examination: cut a sample can, polish the section, measure overlay, body hook, cover hook, tightness, seam thickness, and seam height under a microscope. Acceptance criteria should reference tolerances from the technical agreement. For detailed seam quality methods, see [Double Seam Quality Control](https://canmachine.org/double-seam-quality-control-tin-can-china-2026/).
### 13. Can the line handle different can sizes?
Yes. Most automatic lines support quick changeover within the rated range. For example, Yongxin’s 1–5L small square can line handles diagonal 45–280 mm and height 90–350 mm, with PLC recipe changeover in approximately 5 minutes (plus 15–30 min for physical adjustments and first-piece verification). For specialty shapes, see [Rectangular Can Making Machine Guide](https://canmachine.org/rectangular-can-making-machine-china-2026/).
### 14. What certifications are needed for EU import?
Machinery must comply with **Machinery Directive 2006/42/EC** and bear CE marking. The supplier should provide a Declaration of Conformity and technical file referencing **EN ISO 12100:2010** and **EN 60204-1:2018**. Confirm CE requirements before ordering. For chemical can applications, see [Chemical Tin Can Making Machine](https://canmachine.org/chemical-tin-can-making-machine-china-2026/).
—
## Related Articles
– [How to Start a Tin Can Manufacturing Business in China (2026)](https://canmachine.org/how-to-start-tin-can-manufacturing-business-china-2026/)
– [Tin Can Making Machine Price Guide: What to Expect in 2026](https://canmachine.org/tin-can-making-machine-price-guide-china-2026/)
– [How to Choose a Tin Can Making Machine Manufacturer in 2026](https://canmachine.org/how-to-choose-tin-can-making-machine-manufacturer-china-2026/)
– [Tin Can Making Machine Maintenance: A Preventive Approach](https://canmachine.org/tin-can-making-machine-maintenance-china-2026/)
– [Double Seam Quality Control for Tin Can Manufacturing](https://canmachine.org/double-seam-quality-control-tin-can-china-2026/)
– [Rectangular Can Making Machine: Complete Guide](https://canmachine.org/rectangular-can-making-machine-china-2026/)
– [Chemical Tin Can Making Machine: Equipment for Industrial Packaging](https://canmachine.org/chemical-tin-can-making-machine-china-2026/)
– [Production Lines — Full Range Overview](https://canmachine.org/production-line/)
—
*Disclaimer: This article provides general technical and commercial guidance based on industry practice and Jiujiang Yongxin Can Equipment Co., Ltd.’s experience. It does not constitute legal, financial, or engineering advice. All specifications referenced are based on Yongxin’s published product parameters and are subject to change; confirm final specifications in the technical agreement.*